NGD has wide diagnostics experience at different facilities. As of 2017, total length of subsea pipelines inspected by our company is 5 408 km.
Each year our company inspects about 4,500 - 5,500 km of above-ground pipelines, multi-diameter pipelines among them, including with the use of compressors.
Contract commencement:
15.06.2020
Contract completion:
31.12.2020
Customer:
Irkutsk Oil Company
Contract description:
Ø 219 and Ø 820 gas pipelines MFL/TFI smart pigging.
Total length of pipelines — 40 572 m.
Contract commencement:
01.04.2020
Contract completion:
31.12.2020
LLC ""RN-Yuganskneftegaz""
Lenina St., 26,
Tyumen Region,
Nefteyugansk, 628309,
Russia
Tel.: | +7 (3463) 315 – 201 |
Fax: | +7 (3463) 228-951 |
Email: | rn_yng@yungjsc.com |
Inspection of the oil pipelines Dn 219, 273, 325, 426, 530, 720 by acoustic-resonance method in order to identify unauthorized tie-ins.
Total length of pipelines — 120,0 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.06.2020
Contract completion:
31.05.2022
Contract description:
Inline inspection of the ethylene pipeline using MFL tool.
Industrial safety review of MEP sections, ball valves DN200 PN 160, DN50 PN 16, block valve stations DN50 and water crossings.
Pipelines length - 214 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
16.06.2020
Contract completion:
31.12.2021
Customer:
ООО LUKOIL - Komi
"Yareganeftegaz"
169710, Republic of Komi,
Usinsk,
Neftyanikov st., 31
+7 82144 5-53-40
Contract description:
Smart pigging of Ø 325, Ø 530 oil pipelines.
Total length of pipelines — 159.09 km.
NTC status: Contractor
Contract commencement:
22.06.2020
Contract completion:
21.09.2020
Contract description:
Smart pigging of main gas pipeline.
Pipelines length - 22.7 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.07.2020
Contract completion:
25.10.2020
JSC Verkhnechonskneftegaz
Calibration, linear part cleaning, multi-channel profilometry with navigation and smart pigging of the main oil pipeline "Vankor field - PS Purpe" ⌀820 mm.
Tel.: | +7 (3952) 289 920 |
Email: | vcng@rosneft.ru |
Pipelines length - 40,785 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.01.2020
Contract completion:
16.03.2020
OOO "RN-Vankor"
Calibration, linear part cleaning, multi-channel profilometry with navigation and smart pigging of the main oil pipeline "Vankor field - PS Purpe" ⌀820 mm.
Pipelines length - 402,8 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
20.12.2019
Contract completion:
30.06.2020
Customer:
Tel. | +7(342) 235-64-53 |
Contract description:
Pre-start inspection of a gas pipeline Ø426 mm: pigging, calibration, profile logging, MFL inspection.
Total length of pipelines — 30,4 km.
NTC status: Subcontractor
Contract commencement:
10.03.2020
Contract completion:
30.06.2021
Customer:
OOO «Stroykontrakt»
142703, Rossijskaja Federacija,
Moskovskaja oblast', Leninskij rajon,
gorod Vidnoe, ulica Donbasskaja 2, str. 1
+7 (495) 223-30-45 |
stroykontrakt@bk.ru |
Contract description:
Pre-start in-line inspection of Ø426 mm condensate pipelines at intersections with communications, railways and roads.
NTC status: Contractor
Amount of works under the agreement: 100%
Contract commencement:
14.05.2020
Contract completion:
31.12.2020
OOO «Himremont» | |||
Russia | |||
634067, Tomskaja oblast', | |||
Tomsk, | |||
|
Contract description:
Prestarting smart pigging (MFL + TFI), hydraulic tests, drying and filling with nitrogen of the main gas pipeline Ø1220 mm.
NTC status: Contractor
Amount of works under the agreement: 100%
Contract commencement:
21.10.2019
Contract completion:
30.09.2020
Customer :
ООО "LUKOIL - Nizhnevolzhskneft"
414000, Astrakhan,
Admiralteyskaya st., 1, bldg. 2
Tel.: +7 (8512) 402 8378
Contract description:
Smart pigging of subsea infield multiphase pipeline, subsea infield water pipeline, subsea infield gas lift pipeline, subsea oil pipeline Dn 559, Dn 406, Dn 168, Dn 325.
Total length of pipelines — 75,64 km.
NTC status: General contractor
Contract commencement:
01.08.2019
Contract completion:
28.02.2020
Customer :
ООО "LUKOIL - Nizhnevolzhskneft"
414000, Astrakhan,
Admiralteyskaya st., 1, bldg. 2
Tel.: +7 (8512) 402 8378
Contract description:
Dn 325, Dn559 offshore pipeline smart pigging.
Total length of pipelines — 288,804 km.
NTC status: General contractor
Contract commencement:
25.03.2019
Contract completion:
31.08.2019
OAO "Volgogaz"
|
Contract description:
MFL, TFI, EGP inspection of gas pipeline ⌀530 mm.
Pipelines length - 76,076 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.05.2019
Contract completion:
31.07.2019
CJSC Rospan International
Address: Geologorazvedchikov St., 16 V,
Novy Urengoy, 629306,
the Yamalo-Nenets Autonomous District
Russia
Tel: +7 (3494) 24-37-25, 24-36-00
Fax: +7 (3494) 94-71-32
E-mail: cdo-rospan@rosneft.ru
Contract description:
Preservice smart pigging of ⌀1220 mm external gas pipeline.
Pipeline length - 54,5 км.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
09.04.2019
Contract completion:
31.07.2019
Contract description:
Inline inspection of the oil pipeline ⌀219, ⌀325 mm.
Pipelines length - 40,5 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
18.03.2019
Contract completion:
31.12.2019
Customer:
OOO "LUKOIL – West Siberia"
Contract description:
Smart pigging of Nivagal'skoe oil field gathering line ⌀325 mm.
Total length of pipelines — 1000 m.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.04.2019
Contract completion:
31.12.2021
Customer:
ООО LUKOIL - Komi
169710, Republic of Komi,
Usinsk,
Neftyanikov st., 31
+7 (2144) 55-444
+7 (2144) 55-485
+7 (2144) 55-182
Contract description:
Smart pigging of the TPP "LUKOIL-Usinskneftegaz" field pipelines.
Total pipelines length - 523,509 km.
NTC status: General contractor
Contract commencement:
06.03.2019
Contract completion:
31.12.2021
Customer:
ООО LUKOIL - Komi
NShPP "Yareganeft"
169710, Republic of Komi,
Usinsk, Neftyanikov st., 31
+7 821 445 53 60
Technical diagnostics and industrial safety expert review of the field pipelines.
Length of pipeline — 10,599 km.
NTC status: General contractor
Contract commencement:
01.03.2019
Contract completion:
31.12.2021
Customer:
OOO "LUKOIL-PERM"
614990, Perm,
ul. Lenina 62
Contract description:
Technical diagnostics and industrial safety expert review of the field pipelines.
Length of pipeline — 464,373 km.
NTC status: General contractor
Contract commencement:
28.03.2019
Customer:
OOO "LUKOIL – West Siberia"
Contract description:
Pigging, profile logging and inline inspection of the Ø 1220 main gas pipeline "Pjakjahinskoe m.r. - Nahodkinskoe m.r.".
Length of pipeline — 104,520 km.
NTC status: General contractor
Contract commencement:
18.02.2019
Contract completion:
31.12.2021
Customer:
ООО LUKOIL - Komi
TPP "Uhtaneftegaz"
169710, Republic of Komi,
Usinsk, Neftyanikov st., 31
+7 82144 55 360
Contract description:
Technical inspection and industrial safety review of oil and gas equipment.
NTC status: General contractor
Amount of works under agreement: 100%
Contract commencement:
20.05.2018
Contract completion:
04.12.2018
Contract description:
Industrial safety review and smart pigging of the oil pipeline Ø273 mm.
Pipelines length - 51,812 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
23.11.2018
Contract completion:
14.12.2018
OOO "Garant-Sojuz" | |
Russia +7 (8512) 54-29-69 |
Contract description:
Diagnostics and Industrial safety expert review of the Vertical Stock Tank with Pontoon VSTP-4800.
NTC status: Contractor
Amount of works under the agreement: 100%
Contract commencement:
02.02.2018
Contract completion:
31.12.2018
Contract description:
Pigging of the Ø 530 mm. oil pipeline .
Pipelines length - 27,431 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
01.03.2018
Contract completion:
31.12.2018
Contract description:
Inline inspection of the ethylene pipeline using MFL tool.
Pipelines length - 102,758 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
07.03.2018
Contract completion:
25.04.2018
Contract description:
Inline inspection of the oil pipeline ⌀325 mm.
Pipelines length - 96 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
22.05.2018
Contract completion:
03.12.2018
Contract description:
Industrial safety review and smart pigging of the oil pipeline from oil gathering facility "Romanovo" to integrated oil terminal "Izhevskoe" Ø219 × 8 mm.
Pipelines length - 28,976 km.
NTC status: General contractor
Amount of works under the agreement: 100%
Contract commencement:
30.05.2018
Contract completion:
01.08.2020
Customer:
Irkutsk Oil Company
Contract description:
Ø 219, Ø 273, Ø 820 oil and gas pipelines MFL/TFI smart pigging on "Yaraktinsky" and "Ichyodinsky" oilfields.
Total length of pipelines — 82,37 km.
Contract commencement:
01.07.2018
Contract completion:
05.07.2020
Customer:
OOO "LUKOIL – West Siberia"
Contract description:
Inline inspection of the Ø 219, Ø 325, Ø 426, Ø 530 TPP "Uraineftegaz" oilfield pipelines.
Total length of pipelines — 155,384 km.
27.03.2016 - 05.04.2016 Viktor Leshchenko, Director General “NTC “Neftegazdiagnostika” LLC, visited Calcutta (India) to participate ...
A sole agency agreement was signed between NTC NEFTEGAZDIAGNOSTIKA LLC and Abdel Hadi Abdullah Al-Qahtani & Sons Company
On September 12, the laboratory VNIPI "VZRYVGEOFIZIKA" conducted New website launched! Inline inspection of main gas line Nord Stream pipeline 1-East, Dn 1220×34.6/41 mm, 1224.4 km long Inline inspection of main gas line Nord Stream pipeline 2-East, Dn 1220х34.6/41 mm, 1224.4 km long Segment 1, gas pipeline Ø 1220 mm. OPF – BS-2, 295 km long. Segment 2, gas pipeline Ø 1220 mm. BS-2 – OET, 328 km long. Inline inspection of the offshore oil pipeline "OIFP D-6 – oil gathering facility "Romanovo", Dn 273x18, 51.812 km long. Integrated diagnostics of sub-sea oil pipeline "OIFP – SPM, oil field n.a. Yu. Korchagin" started. Installation and dismantling of temporary pig launchers/receivers Pipeline cleaning, gauging, geometry inspection, magnetic pig inspection Subsea external inspection using ROVs Cleaning of the offshore oil pipeline "OIFP – SPM, oil field n.a. Yu. Korchagin", Dn 325×16.